Eskom is battling to repair a conveyor belt feeding the Medupi units and says any breakdown elsewhere will lead to load-shedding. File image
Image: 123RF/Choneschones
Loading ...

After two nights free of load-shedding, Eskom has warned the country there is a heightened risk of power cuts on Thursday.

“Last night, a conveyor belt feeding coal into the Medupi generation units failed ...

“This means the four generation units in service are not able to take in the requisite amount of coal to generate electricity.

“This puts further strain on Eskom’s ability to fully supply electricity over the next 24 hours.”

Eskom said repairing the conveyor belt is expected to take the better part of the day.

“Any further breakdown elsewhere in the generation fleet would necessitate the implementation of stage 2 load-shedding at short notice,” the utility warned.

On Wednesday night, Eskom was able to suspend load-shedding for a second night in a row after its technicians had returned some generation units to the grid. Enforced power cuts had, however, been in effect during most of Tuesday's work hours. The latest round of load-shedding began last week.

TimesLIVE

The video could not be loaded.

The department of mineral resources & energy has started the process to procure 2,000MW of “emergency power” and R40bn in investment. The department said it is an “emergency power procurement programme”, but in the finer details the power is set to only kick in from about June 2022. Here's what you need to about SA's 'emergency power' procurement.
Loading ...

Loading ...
Loading ...
View Comments