l Moses Mabhida progress at 69% by end 2008
l Moses Mabhida progress at 69% by end 2008
l Peter Mokaba progress at 55% by end 2008
l Soccer City progress at 64% by end 2008
l Green Point progress at 38% by end 2008
l Mbombela progress at 61% by end 2008
l Nelson Mandela progress at 70% by end 2008
Some of the major highlights in the preparations are as follows:
Host Cities have identified training venues and upgrading has commenced with the set completion date of March 2009.
2009 FCC match venues progress:
l Ellis Park progress at 80% (Trencon) and 98% (Rainbow) by end 2008. Royal Bafokeng progress at 64% by end 2008. Mangaung progress at 80% by end 2008. Loftus progress at 80% by end 2008.